Oh okay, so at the end of the manufacturing there is non-zero chance that “oh crap, they aren’t up to scratch” may happen and the whole batch has to be redone, incurring another big delay.
so has the manufacturing of the extruded chassis already started? Sounds like you already have a fixed factory and since there aren’t going to be any checks until it’s all done, is there anything stopping you from starting already?
There's always a non-zero chance; however, it's would be most painful to the factory since they will have lost both the deposit and the balance payment, so it's definitely in their best interest to do a good job ?
It has not started just yet, but we're getting there
Since CNC and Extrusions have to be made at the same time (ensure same batch material and anodizing baths), as well as assembly of all components, we need to put it all under the same order. Since we're going to put it under the same order everything must be super clear (technical drawings and assembly instructions) and protected (NNN, manufacturing and mold-ownership contracts in Chinese) otherwise we run into the risk of losing the deposit (in case of bad quality) or the factory leaking/selling some of our MJOLNIRs themselves.
All this considered, I definitely believe the factory will do a great job (as they have done with the samples) ? As of right now I'm finalizing the assembly instructions while Denize is waiting for the Chinese manufacturing contracts, so we're getting really close. There will be some final price negotiations once everything is signed, but this usually doesn't take more than ~2 days.
I know all this sounds like a PITA, but it's done to avoid newb mistakes I've seen in a bunch of other manufacturing startups. 1000+ MJOLNIRs on the line ?