Since we are almost coming up to the 1 year delay mark from the original Kickstarter estimated delivery date, here is a summary of things that are supposed to be happening this week, how long the team thought it would take, how long it actually took, and my forecasted schedule.
Anticipated progress of this week
- All stealth units and their booster cells packed
- Packing of steel and dark to commence
- Alex receives stealth QC units
- Decision of whether stealth units will be sent out prior to dark and steel colors
Recall of factory schedule vs. reality
Schedule: Workers to start work on Feb. 20th, packing to require 2-3 weeks of work (750 man hours), then shipping.
Claimed case operation rate: 200-300 cases per week
Reality: 630 units completed supposedly on April 10th (not confirmed) meaning that it took 35 working days to complete 60% of the cases
Calculated case production rate: ~100 cases per week
Conclusion: Either the factory only started assembling the stealth cases on the last week of March (i.e. it took more than a month to setup the assembly stations) or the actual case packing rate is significantly lower than claimed rates.
Projected Schedule based on current rate of progress
Dark (~300 cases) packing time: 17 working days (lets say 3 weeks)
QC Shipping of Dark: +0 days (happens during Steel packing)
Steel (~100 cases) packing time: 6 working days (lets say 1 week)
QC shipping of steel: 1 week
Potential PostNord Screwups: 1 week
My guesstimated schedule
QC confirmation and freight negotiations for stealth to take whole of this week
If positive, the stealth cases start getting shipped out next week (a good marker for this is whether address confirmations happen or not)
Batch 1 backers and pre-orders for Stealth only start receiving their cases end of April/Beginning of May
Dark and Steel to be packed, QCed, and greenlighted optimistically last week of May
These orders start getting received in Early June
The sea vs air frieght logic to me does not make sense as the only reason why ThorZone would choose sea freight would be to save money, and to do this the backers must endure potentially 4-6 weeks of additional shipping time on top of waiting for all colors to be finished since it would have to be shipped together to make sense. So it really sounds like, this should be really reserved as a last resort if you cannot complete the project without taking this route (anything else is going to be interpreted as a reflection of chasing profits) so the only way forward with respect to shipping is to either ship them by air all together (i.e. all colors) or as they are done, meaning that select backers and pre-orders will receive their case before backers.
This technically is in breach of the kickstarter campaign rewards of "receiving the case 6 months before non-backers", even ignoring the fact of 6 months clause, if somebody who pre-ordered (non-backer) a single stealth Mjolnir S gets their case before (potentially by a month or more?) somebody who backed Mjolnir Duo tier through kickstarter, I think they really need a sincere apology and explanation as to why their contribution and patience is being taken advantage of despite them having waited longer, and technically promised an earlier receiving of the case. At this point I don't know if anybody is seriously considering writing a serious review of the case, but the timeliness of the review article would be hampered if you didn't order a single color that happens to be stealth.