Update after 2nd week of Sentry manufacturing process.
a) new power button cables with professional sleeving:
We also made "some" orders. Here's a list:
- IEC power cables,
- power buttons with new professional wires sleeving,
- laser engraved aluminium labels,
- aluminium 2,4 mm rivets for engraved labels,
- all types of M3 mounting screws (nearly 100 000 pcs),
- binding screws for mounting the vertical stand,
- rubber O-rings for vertical stand,
- plastic feet for horizontal mounting,
- plastic covers for holes unused in vertical position,
- PCI slot covers,
- rubbers for fastening internal cables,
- silica gels,
- industrial glues (Loctite 243 and Loctite 480),
- Sentry transport foil bag,
- zipper foil bags,
- printing tapes for thermal small labels printer,
- big labels for thermal printing of shipping information,
- thermal printer for printing shipping labels,
- black stretch foil for packaging purposes,
- packaging tapes,
- transport baskets for internal transportation process,
- 2 mm allen wrench.
On Friday we sent instructions to our metal parts manufacturer how to pack everything on the euro pallets (we mentioned it before). At this moment we are waiting for our first two Sentry v1.1 preproduction prototypes. Our subcontractor will manufacture steel elements, and after our quality control he will make those over 1000 Sentry cases according to those 2 checked units (one painted black and one prepared for painting white in external paint shop).
Finally, you asked if the delay made by indiegogo in sending your contributions will influence the starting time of our package shipping. At this point we do not really know, but we can assure you that we are doing our best (including working 13-16 hours a day) to start sending your Sentry cases according to the plan, in April. If we will notice a situation where something will slow us down, as always we will let you know.